The street
inventory contains approximately 52 centerline miles. Annually, the Township Road
District undertakes a windshield survey of each street's degree of cracking and/or
deterioration and the Long Range Resurfacing Plan is adjusted. Consequently, the
roads with the worst pavement conditions are scheduled for resurfacing. Under
our approach, the street system is better maintained at less expense than if gross
deterioration is allowed to occur.
The performance
benchmarks established for street maintenance are to: eliminate all grossly deficient
streets with a "1" rating; rehabilitate as many "2's" as possible
with the funding available; and to maintain a minimum of 70% of the streets with
a rating of "3" or better.
Repairs and maintenance
of the Township Road District street system requires an on-going management program
to identify and prevent premature failure of the pavement base and surface and
to correct problems on a timely basis as they occur. Last year's maintenance and
repair activities included asphalt patching, pothole repairs, sweeping and grading.

|